Overview

Mid South Contractors proudly contributed to the construction of the NextStar Battery Plant, one of North America’s most advanced battery production facilities. With a focus on precision, scale, and energy efficiency, our team played a vital role in the successful execution of this large-scale industrial project.

Our scope of work included:

  • Installing 35,000 feet of cable tray to support plant-wide electrical infrastructure
  • Pulling 90,000 feet of low-voltage (LV) cabling and 80,000 feet of medium-voltage (MV) cabling
  • Deploying over 300 skilled workers at peak manpower
  • Completing 65 substations, including full wiring, torquing, and energizing
  • Installing 54 Power Distribution Panels (PDPs) with comprehensive electrical integration
  • Conducting extensive SCADA system installation and retrofitting with associated equipment
  • Performing critical load calculations to meet project-specific power demands
  • Installing complete site-wide lighting systems, including energy-efficient fixtures and temporary construction lighting

This project stands as a testament to Mid South Contractors’ ability to deliver high-performance electrical solutions on time and at scale. Our team’s expertise and dedication helped power the future of clean energy manufacturing in North America.

Client

NextStar

Location(s)

  • 9655 Twin Oaks Dr, Windsor, ON N8N 5E8, Canada

Subsidiaries/Partners

Date Completed

Ongoing

Markets

back to top