Overview

An integral part of Henry Ford’s River Rouge automobile complex, the steelworks facility, was purchased by Severstal North America in 2004. The plant has been in operation since the 1920s and produces high-quality flat-rolled carbon steel products; hot and cold rolled sheet, hot-dipped galvanized and electro-galvanized sheet, and other advanced steels.

$740 Million Plant Modernization
Severstal made many significant improvements to the plant, including a $740-million modernization program completed in 2011. That modernization project included constructing a state-of-the-art pickle line tandem cold mill (PLTCM) complex and a hot-dip galvanizing line (HDGL).

Design Assist, EPC, and BIM
General contractor Barton Malow selected Motor City Electric Co. as the electrical contractor for both of these complex projects handling design-assist, material procurement, installation, testing, and commissioning support. This project required collaboration and coordination among all building trades and incorporated Building Information Modeling (BIM) for the planning, design, and construction of the facility and infrastructure.

Client

Severstal

Location(s)

  • 4001 Miller Rd, Dearborn, MI 48126, USA

Subsidiaries/Partners

Markets

An Enormous Steel Production Facility
The PLTCM stretches more than one-third of a mile and includes a complete and complex electrical system for power and lighting. The new facility covers 500,000 square feet and includes:

  • Substation and transformer yards
  • A PLTCM process area
  • A roll shop
  • Coil handling and band staging areas
  • One tandem cold mill and two pickle line electrical rooms
  • Utility/emulsion and hydraulic pump rooms

The PLTCM project consisted of power/control cabling installation and equipment reconnect for the coil handling, pickle line, and cold mill systems:

This included:

  • Design and installation of an extensive cable tray distribution system
  • More than 41,000 feet of cable tray and its required support system
  • Renovation of an existing 35kV outdoor substation yard
  • Power distribution via cable tray on a 1,400-foot long trestle to three main 35kV/15kV transformers
  • More than 140,000 feet of 35kV cable
  • 27,000 wire terminations
  • Nine 480V processes and related power distribution load centers
  • 21 15KV/5K and 15kV/600V transformers
  • Motor control centers
  • 24 HVAC units
  • 11 overhead cranes
  • Process equipment electrical panels
  • Uninterruptible power supplies (UPS)
  • More than 1,200 light fixtures
  • Over 200 120V 20A utility receptacles
  • 55 480V 60A weld receptacles
  • 14 powered overhead doors/air curtains

This incredibly complex project was not only completed three months ahead of schedule but also safely and accurately through the coordination and management of the workforce and ongoing tracking of materials, costs, labor, and productivity.

back to top